🚧 **Porter Street Update: Progress, Framing, and Paving!** 🚧
Today, we had a fantastic visit from **Mike Rybicki**, our lead engineer with MLR Engineering on the "Trail of Two Cities" connector Pathway Project! Mike stopped by to present us with some beautifully framed snapshots of the Trail construction done by Wilcox Contracting LLC of Beaverton along Porter Street. It’s amazing to see how far we've come! 📸 This initiative would not have been possible without the 100% Funded CMF DNR SPARK Grant for "opportunity communities" to create public outdoor recreation spaces!
CMF/DNR Spark Grants Program Partnership | Council of Michigan Foundations https://share.google/iZlqTm6Ytq8Txu9Wr
First, we want to say a huge **THANK YOU** for your patience. We completely understand how frustrating the road closures and detours have been. Not to mention those not following the posted detours. 🤔
We wanted to share a quick update on where things stand and why the timeline shifted slightly:
* **Why the wait?** First came the Trail, then the water main project. Right now, we are waiting on asphalt.
* **A better road ahead:** We actually decided to *expand* the paving project! This means we are paving more of the road and giving residents and businesses a much better, smoother approach to their driveways.
* **The delays:** A mix of multiple heavy rain events, extreme summer heat, holidays, and competing MDOT projects (which take priority for asphalt crews) pushed our paving schedule back by a few weeks. **Plus, we definitely didn't want the heavy 4th of July traffic coupled with that intense heat to ruin a brand-new road before it even had a chance to cure!** ☀️🇺🇸
We promise the wait will be worth it! Stay calm and hang in there—the final paving is happening very soon! 🦺🚜