‼️Loch Erin Home Update‼️
•Exterior ✅ (Stone will be done tmr)
•Deck Railings✅ (Waiting on screens to finish two small spots)
•Basement flooring, cabinets, doors, trim and tile✅
•Under Deck dry space✅
•Gutter Downspouts Piped to lake✅
•Multiple French drains✅
•Retaining wall drains piped to lake✅
•Final Grade/Seeding (1/2 way done)
•Bringing in screened topsoil for a good start for the grass
•First floor:
-Flooring✅
-Cabinets (Started)
-Interior doors✅
-Trim (started)
-All exterior doors✅
-Bathroom tile✅
Lots to go, keep knocking stuff out everyday!