Well its in the books finally and now I can post about it. This job is a 6k foot run we did at Craney Island in Portsmouth. We had to leave and come back due to a hold up on a gas crossing permit.
On this one the team pulled double 1.25" conduits 6k feet across the entire facility. We really enjoyed this one as there was a lot of emptying rod racks.
The team did a wonderful job as always and we finished the install with zero issues. The client will come next week and set boxes and pull wire. This project was to wire up gate controls for added security.