07/24/2026
Over or under $10,000.00? 👀
•
•
Day 1: 11hrs - 4-man crew
1. Till and remove poor fill: 2hrs - 12yds
2. Grade and add topsoil: 3hrs - 8yds
3. Lonche: 30 min
4. Lay sod: 3.5hrs - 13.5 pallets
5. Set up and clean up: 1.5hrs
6. Drive time: 40min
Day 2: 4hrs - 2-man crew
1. Wash stone and metal edging - 3hrs
2. Drive time: 40 min
•
•