01/14/2025
Check out these floors!
This project presented unique challenges with the placement of PrīmX slabs, which have square footage limitations and require a 72-hour wait between adjacent pours due to their expansive properties.
Through strategic planning and strong collaboration with fellow trades, we maintained a pouring schedule of 3 to 4 pours per week while also installing over 15,000 linear feet of sinus armor joint.
This enabled us to complete 1,122,156 square feet of slab placement over the course of 3 months.
Our coordinated approach ensured that we met these demands on schedule while upholding the quality and precision required for PrimX installations.