08/28/2026
🚧Friday feels like a good time to look back at one of our recent project completions. 👀
Our PennDOT King Hill Road Culvert project has been wrapped up for a few weeks now, but this transformation is worth another look. 🔍
In under one month, our crew closed the road, removed the existing culvert, installed the new box culvert, profiled over 650 feet of roadway, completed full pavement and drainage restoration, and had King Hill Road reopened to traffic. 😤
A fast-paced project with a lot packed into a short schedule — and a finished product our crew can be proud of. 👌🏼
From road closed to job complete in under 30 days. That’s a solid way to head into the weekend. 🔥