As the Prime Contractor, Bietz Moving Dirt, LLC successfully delivered:
• 8,800 LF of new access roadway
• 80,000 CY of compacted structural fill
• 43,000 CY of stripped and stockpiled topsoil
• 30,000 tons of subbase and base aggregate placement
• 510 LF of combined CMP culvert installation
In partnership with our paving Subcontractor (Croell, Inc.), they placed:
• 23,848 Square Yards of asphalt surfacing