08/06/2026
Rough plumbing for phase two is complete and inspected at the Hudson American Legion- complete new plumbing for the two main level bathrooms as well as the kitchen, upsized water main, extensive plumbing replacement in the mechanical room with clear isolation for each area of the building, new water piping up to the third floor bathrooms, and the addition of a grease trap for the dish sinks and food prep sink. Also included are some photos of our finished work in the lower level bathrooms from earlier this year