3,750 LF of force main. 12 access pits. 9 weeks. 2 phases.
In Riviera Beach, our crews pipe burst a failing 16-inch cast iron force main and upsized it to an 18-inch HDPE. Excavation was limited to 12 access pits instead of a continuous trench through residential streets. Combined, the pits spanned about 120 LF, roughly 3 percent of the alignment, and totaled about 160 cubic yards of excavation. An open-cut trench of the same depth would have required more than 15 times that volume, even assuming a narrow 3-foot width with vertical walls.
Phases I and II took a combined 9 weeks from mobilization through restoration, well ahead of the original anticipated timeline.