08/19/2026
In 2015, a resort mountain airport in Heber City, Utah brought Ardurra on as its engineering consultant. Nobody was talking about the Winter Olympics...yet.
After years of population growth, the airport's future needs were becoming impossible to ignore. In 2019, Ardurra began a planning effort to reevaluate the airport. Through a comprehensive, 4-year master planning effort, Ardurra confirmed the airport would need an Airport Reference Code (ARC) upgrade and identified the infrastructure improvements required to support that
transition and future demand.
The plan outlined a major transformation ahead: a relocated runway, a relocated taxiway, increased separation from the adjacent highway, and other critical improvements needed to position the airport for 2034 and beyond.
Heber City has now selected Ardurra to lead that work. That's $80 million in capital improvements, five years of implementation, and one major deadline nobody wants to miss.
This is the work we love. Taking an airport we've grown alongside since 2015 and helping prepare it for one of the biggest stages in the world.
Happy National Aviation Day. Here's to the next five years.