05/29/2026
Next studio apartment is completed. Passed final inspection with the building department this morning. Apartment #5 of 8. 3 more to go! This one was frustrating. Two different contractors did some work. There were some issues and the apartments got demo'd, 2 different contactor did that. With the sheetrock demo'd, it exposed the first 2 contractors work and wow. No permits were pulled for the framing. Work was done by contractors who are a whole lot bigger then my business. Had Tim Henry do an inspection. Pulled a permit to fix the framing and put the unit back together.
Fixed the framing, Twins Electric re wired the unit. Installed insulation, sheetrock, mud, tape, texture, prime and paint. Flooring was installed. Installed cabinets, countertop and trim. Cleaned up and this one is done!
Unit is already rented for the first of the month.