10/11/2026
Even on a 3 ac. lot I’m dealing with setbacks. I don’t like guessing especially in a county that doesn’t seem to like me, so I brought out the professionals. I asked the surveyor to provide a few things for a successful build:
1. SETBACK: Even on a 3 acre parcel, my setbacks are tight.. From my property line, I have a 30’ right of way for the county and a 25’ setback. That leaves me 55’ off the property line before I can put a structure down. The property line is in the middle of the street somewhere, so I had my surveyor put down lines at 55’ relative to the building pad to reference when batter boards go down.
2. BENCHMARK ELEVATION: This is a starting point for any elevation measurement needed on the property. This one is set at 2,392’, which is my finished floor height. I can subtract 8” for my pad elevation, regardless, everything’s pulled off that elevation.
3. OFFSET STAKES: In construction, control lines help determine building location. I had him stake out the left side of the building. The accuracy they’ve got is far better than anything I’ve got available. I’ll batter board through these pins and since they’re 5’ offset from the building corner, they won’t be in the way when doing the foundation. I’ll square off this line to get every other line necessary for my building, Pythagorean Theorem who?
I’ll share more on how these play a role in building as we go!