We are off to a good start on our water main replacement project in Wayne. We are replacing water mains and services up to the ROW on Logan, Nebraska, and Windom Streets from 7th St (Hwy 35) to 10th St in the middle of Wayne. In all, 9 blocks of water main and 76 services will be replaced. This is a large, and much needed, investment in Wayneās infrastructure.
Due to brick streets, several established trees, and tight working conditions this project is mostly being built by directional drilling of the pipe. A directional drill pushes a steerable rod into the ground and pulls back the pipe. While normally more expensive than open cut installation, projects like this show enough savings in restoration of the streets, driveways, and landscaping to make it a viable option.
Bauer Underground of Norfolk is performing the directional boring for us on this project. In the beginning of the video you can see their drilling rig set up and pulling pipe back. Our crew is on the other end installing pipe and helping with the pulling process. Once the water main is in we will dig in any pipe necessary and make connections to the mains. After testing the mains we will dig up services and Bauer will help with boring those also. After all pipe is installed and operational we will unhook the old mains and abandon them. Concrete sidewalks, paving, and replacement of brick paving will be performed by Jerico LLC of Pender and seeding will be performed by Autumn Custom Seeding of Dakota City.
We appreciate The City of Wayne trusting us to take on a project like this in their town. We have a great team of subs and suppliers and weāre looking forward to working in Wayne the next couple of months.