This project has been ongoing, and it’s involved several stages of repair. After the water and fire damage crew completed their work, E&A Custom Construction installed new insulation in the affected areas, rerouted the water line for the water heater through an interior wall, connected the new water heater, and installed new subflooring and drywall.
As we continued the work, we found additional drywall with visible mold inside and outside the wall. The remaining affected drywall had to be removed as required by the insurance work.
We’ve now installed new LVP flooring from the kitchen through the laundry room so the customer can move their washer and dryer back inside before the bad weather arrives. Next, we’re masking the area and getting ready to mud, tape, and texture.
Another step closer to getting this home back in shape! Evan Avila E&A Custom Construction LLC Adriana Rincon