Fire station update: Insulation is installed, plumbing installation is ongoing, and sheetrocking has started.
04/06/2026

Fire station update: Insulation is installed, plumbing installation is ongoing, and sheetrocking has started.

04/05/2026

Condolences to Walnuttown Fire Dept, family and friends. R.I.P. Chief Buck and Assistant Chief Shick. πŸ™πŸΌπŸ˜’

04/04/2026

April is Distracted Driving Awareness Month

Distracted driving takes lives, devastates families, and impacts entire communities. Every text, call, or glance away from the road can have serious consequences.

To help make a difference, Responder Safety Learning Network has put together resources to support your Community Risk Reduction (CRR) and public education efforts focused on stopping distracted driving.

Take a look and share. https://tinyurl.com/mvda8rd8

Sad news😒 R.I.P Andy
04/02/2026

Sad news😒 R.I.P Andy

Molloy, a fill-the-room personality with connections in every Maine corner, worked for the KJ for 3 decades, framing fires, elections and everything in between.

Update on fire station: Ground work is resuming to bury the propane tank while plumbing, electrical, and air duct instal...
03/31/2026

Update on fire station: Ground work is resuming to bury the propane tank while plumbing, electrical, and air duct installations are in progress.

The new fire station is progressing well. Roofing is finished, stairs for the second floor have been installed, and elec...
03/28/2026

The new fire station is progressing well. Roofing is finished, stairs for the second floor have been installed, and electrical work is almost complete.

03/25/2026

Upcoming chicken bbq! Tickets are available online at the link below. Also in person pre sale tickets available. See a member!

https://square.link/u/pBxWdJw6

The storage and mechanical rooms have been framed. The administration roof is complete, and the truck bay roof is nearin...
03/25/2026

The storage and mechanical rooms have been framed. The administration roof is complete, and the truck bay roof is nearing completion. Installation of stairs to the mezzanine is underway, and electrical, communication, and IT wiring are being installed. Excellent work by all. πŸ‘πŸ‘

03/24/2026

Learn to Read the Smoke

03/24/2026

Address

Randolph, ME
04346

Telephone

207-582-9844

Website

Alerts

Be the first to know and let us send you an email when Randolph Maine Fire Dept. posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share