Meet the Project Team delivering two major renovation programs for Baylor Scott & White Health in Plano.
Across Baylor Scott & White The Heart Hospital and Baylor Scott & White Regional Medical Center, one coordinated team is completing six renovation scopes totaling more than 50,000 SF within active patient-care environments.
At The Heart Hospital, the 13,524 SF program includes:
▪ A five-phase renovation of the 10,454 SF ED, including patient exam rooms, nurse stations, restrooms, and redesigned reception area.
▪ Renovation of a 1,800 SF second-floor physician’s lounge, including a Surgeon War Room and improvements to staff dining and lounge spaces.
▪ Renovation of a 1,270 SF Cath Lab 4 suite, including a Philips cath lab system, Stryker equipment, control room, and workstation.
At the Regional Medical Center, the 37,000 SF program includes:
▪ Phased renovation of 10 operating rooms across 17,000 SF, with interior finishes and Stryker equipment supporting greater connectivity, safety, and patient care.
▪ A two-phase renovation and expansion of an 8,500 SF interventional radiology department, including Siemens and Stryker equipment.
▪ Renovation and expansion of an 11,500 SF ED to increase capacity and support the hospital’s evolving needs.
What makes this work complex?
▪ Each scope is completed within an active healthcare facility where patient access, clinical operations, safety, and continuity of care must remain a priority.
▪ At The Heart Hospital, the ED will move through five phases, requiring hospital staff to continually adapt as work areas and circulation routes change. At the Medical Center, the OR renovations are being delivered in eight phases, requiring the team to remain flexible while protecting ongoing surgical operations.
▪ Shutdowns, equipment installations, infection-control requirements, Interim Life Safety pathways, and facility impacts must be carefully planned.
▪ Weekly, in-person coordination with BSW and CBRE facilities team allows the group to review shutdowns and operational impacts across active work.