07/12/2024
7/8/24
Project update #11: Another week, another update. At the interior of the campus we completed our anodized aluminum canopies. In our classrooms we started our final coat of paint as well as our interior trim at doors and windows. In combination with this, we also fired up our VRF and MAU HVAC systems to provide conditioned air to our space while also working on our “T” canopy carpentry out front and finishing up our windows through the installation of trim plates for mullions, sills, and window heads.
Most importantly though, this week we’ve started our roof truss replacement for our cafeteria. Our previous thoughts to reuse the existing trusses in place for our new roof was discovered to be impractical and as such we had to draft a backup plan. Our plan going forward is to replace 32 existing trusses with new trusses of similar aesthetic but stronger characteristics. Notably, because we have finished products beneath our roof truss replacement area and because the existing masonry walls supporting the trusses are 28 feet tall we are having to replace the trusses segmentally as opposed to ripping the entire roof off at once and then reinstalling our new works. In respect of this, we’ve had to build a dance floor scaffolding platform beneath the entire workspace so our guys have a platform to safely work off of as we move forward.