11/27/2025
โPROJECT UPDATEโ
We are thrilled with the steady progress on our 12-unit apartment complex. Each milestone brings us closer to completion, and the entire team is proud to be part of this development. We are confident this property will add exceptional value to the Roaring Fork Valley!
Basalt | Custom Multi-Family | 12-Unit Apartment Complex | 10,994SqFt | 3-Story | 21 BedRm | 24 Bath | River Views
๐ธ
๐ธ
โOVERVIEW OF COMPLETED PROGRESS:
โขFoundation walls poured.
โขFoundation walls sealed, waterproofed, and insulated.
โขBackfill and compaction completed.
โขUnder-slab plumbing installed.
โขConcrete slabs poured.
โขAll underground utilities installed.
โขBuilding fully framed.
โขWindows and exterior sliding doors installed.
โขRoof drains and overflows installed.
โขCommercial flat roof completed.
โขExterior board-and-batten siding installed.
โขExterior painting completed.
โขAll interior walls framed.
โขTemporary stairs installed.
โขExterior decks completed.
โขFire suppression systems installed.
โขSolar lines and sub panels mounted.
โขElectrical rough-in completed.
โขWaste, vent, and domestic water lines completed.
โขExterior ground elevations adjusted.
โขNative soil excavated and removed.
โขParking lot aggregates imported and grated.
โขParking lot sub-grade compacted.
โขParking lot drains installed.
โขConcrete curb and gutter underway.
โNEXT UP:
โขPass all remaining rough-in inspections (plumbing, electrical, mechanical, insulation).
โขInstall insulation throughout.
โขHang, tape, and finish drywall.
โขPrime and paint interiors.
โขFabricate and install custom iron staircases.
โขFinish concrete curb and gutter.
โขForm, prep, and pour sidewalks.
โขInstall metal siding panels.
โขInstall architectural siding accents.