03/20/2026
We’re Back.
Progress Update — Winter Hill Triple Decker
After an unexpected early delay, work is fully underway and we are making up lost time.
In just four days, our crew will have framed two levels of this triple decker and on pace to complete rough framing in under two weeks.
This level of ex*****on shows what an experienced and knowledgeable team can accomplish. Watching this frame come together has been a reminder that a GC is only as good as the subcontractors he hires,
The first plate was set on Tuesday, March 17. By the end of the day Friday, March 20, the second-floor exterior walls are expected to be complete.
Windows and roofing are dropping Thursday March 26, by March 31 we’ll be weather tight.
More progress coming soon.