The Department of Energy defines a Microgrid as "a group of interconnected loads and distributed energy resources with clearly defined electrical boundaries that act as a single, controllable entity with respect to the grid having the ability to connect and disconnect from the grid to operate in both grid-connected or island mode." Project Timeline:
Phase 1:
Island the MicroGrid and sort out l
oad shedding and primary control issues (2015)
Phase 2:
Rule 21 approval for parallel operation (11/2015)
Phase 3:
Partner with PG&E and Sonoma Clean Power to explore community based microgram connection exploring grid/microgrid symbiotic relationship (2016). The primary directive of the microgrid project is to reduce the carbon footprint of the Stone Edge Farm property as well as establish a degree of energy independence. This goal is to be the fundamental design consideration at all times. This goal shall be used for guidance when determining system changes, equipment choices and implementation of work efforts. It is the intent of the parties involved to see how far below zero a 16 acre urban farm can reduce greenhouse gas emissions. Corollary #1
Seek out and find any and all technologies to accomplish this goal. Failure is the crucible of success.
2.) Do not fear failure, embrace it.
3.) We may have to do some things twice, maybe even a third time. Corollary #2
You will not use cost as your first criteria in your decision making process. "Money is like manure; it's not worth a thing unless it's spread around encouraging young things to grow." - Thornton Wilder