04/21/2026
Carpenter, LLC has commenced work at the Budlong Pool project in Cranston, Rhode Island, where we were awarded the trellis scope at the shower area following our 2024 bid.
As some of you may already know the project experienced extended delays due to unforeseen site conditions, including the discovery of an undocumented groundwater/aqueduct system, along with complications involving existing drainage infrastructure. These conditions required additional engineering, coordination, and adjustments to the overall project schedule before construction could proceed again.
As is often the case in construction, timing does not always align perfectly, and this project resumed after a prolonged delay while other commitments were already underway. Our team has since mobilized and working in coordination with our good friends at Vantage Builders to see this one thru, follow us as progress continues on site.