06/17/2026
Sunnyvale, CA โ CSE is making short work of this new project involving the replacement of a 50,000 gallon water tank and accessories. The existing redwood tank has already been demolished and CSE is ready to pour the new tank foundation and then turn the site over to Paso Robles Tank who will construct the new welded steel tank. The CSE team did an outstanding job safely demolishing the tank while dealing with limited real estate. Safety above all else!