01/26/2025
Mountain Barndominm update
From late September we shared pics of the grading and foundation work. Since that time we have been erecting the red iron frame. While the system is bolt together, there are a lot of parts that have to be fit together in the proper order. Since this is a custom build, window & door frames must be custom build and trimmed out on site.
Building in the mountains during the winter also has it’s challenges. Some days it is simply too dangerous to work because of wind or ice. After the frame is complete, with doors and windows trimmed out, we are onto the next step of setting wall panels. Very few of these panels can be set whole, but must be cut and fitted around the doors and windows. We are now ready to install the roof panels and then the project will almost be dried in.