*ATTENTION* UPPER DARBY USE & OCCUPANCY PERMIT APPROVALS CURRENTLY TAKING THREE WEEKS TO OBTAIN!
If you are a realtor, mortgage broker, or agent selling a property in Upper Darby Township, PA and the sewer lateral inspection fails, it will take three weeks to get the permit approved for repairs. Once the permit is approved, the repairs will take one to three days to completeβ if the weather cooperates. Once repairs are finished, it will take one to two weeks to get the U&O approval paperwork from Upper Darby. Together, it will take five weeks to complete sewer repairs and reach settlement.
Last week, we had two property transfers that were supposed to settle on Friday but still donβt have permits.
Permits for repairs or replacements due to U&O inspection failures are not considered emergencies, so it is important to keep these delays in mind. Permits will not be expedited for these reasons.