Lots of work has been completed in the last 2 weeks on this ICF build. With the basement walls being successfully filled with 8” of concrete we were able to move onto waterproofing the outside with prime free protecto wrap. Followed by a 4” French drain around the footing perimeter to keep this basement dry.
2” of foam board underneath the slab with hydronic heating will keep this building at a comfortable temperature year round.
Open web floor joists were completed for the first floor framing with 3/4” Advantech for the subfloor.
We will now be able to stack the remaining ICF block to complete the first floor exterior walls.