03/05/2024
It's always good to finish a project on time it feels amazing to finish a month ahead of schedule.
Road repair and upgrade completed this week.
Original road and paving was severely damaged which lead to the damage of residents vehicles. Over 1400m2 of damaged paving lifted and stored, over 400m3 of clay excavate and replaced with aggregate. New subsoil drain and storm water drains installed. New electrical conduit installed for future fibre. New 80mm interlocker pavers supplied and installed for the roadway and original pavers cleaned and reused around the units.