27/05/2026
By August 6, we successfully delivered 50,000sqm of formwork (horizontal & vertical) and poured over 15,800m³ of concrete, completing Levels 1–9 at an average of 1,500sqm per week as part Nepean Redevelopment Stage 2 – the NSW Government’s major expansion and upgrade of Nepean Hospital. This scope of works showcases the expertise of our site team, who delivered high-level slab construction and cantilevered structures with precision using advanced systems including Peri Rosett, BKH Systems, Ischebeck table systems and bespoke formwork elements. A huge credit goes to our dedicated site team for their outstanding ex*****on and consistent performance, working alongside our valued partners, CPB Contractors, to achieve excellent results on this project.