Great progress out at Waikari (Glenbrook Road) as the new bridge comes together over the awa. The massive steel girders have been craned into place - the backbone of the whole structure - all deck panels have now been placed, and the final concrete pour is underway.
Our Hawkes Bay crew has been panel stitching to interlock each individual concrete panel into one continuous bridge structure - one of the last big tasks for the structures side of this project. Awesome to see it all coming together.
Delivered in collaboration with Wairoa District Council and WSP, we're restoring permanent, reliable infrastructure for the community. And that comes down to the crew grafting away day in, day out. Ka mau te wehi, team 👏