11/01/2026
Trying to get finished up on a few projects before the weather changes for the worse around here. Closing out some topsoil at Heath elementary and just on the last few thousand yds at msu vet. We like about 2,500 of 55,000cy. Just took delivery of almost 6,000’ of storm sewer pipe for the new Murray elementary school. Some big changes coming this week and next at Krogers. We will begin to build the big reinforced slope wall next to mega gym this week. It’s going to be a nice process and the biggest reinforced soil slope wall around this area. We’ve got a lot to get done in a short amount of time before weather starts to get into the rain pattern. Also we’ve got some paving coming up this week stay tuned I’ll post some pics of some driveways and parking lots that we will be making black this week since the rain came in will give us time to catch up on some paving. Anything excavating demolition paving and hauling we got you.
West and middle ky. West and middle tn.
270-293-9084.